Reform of the grid connections process to quickly deliver more renewable energy projects is more critical than ever, according to Ofgem.
The regulator said the new UK Government’s refocusing of efforts towards a new 2030 clean power mission had provided fresh impetus for work to speed up connections.
“With the queue now at 725GW across transmission and distribution, more needs to be done to meet Net Zero objectives,” said Jack Presley Abbott, Deputy Director of System Planning and Connections in a blog post.
“Delays in connecting customers exceed five years, taking connection dates well beyond 2030 and making it clearer than ever that we need to act now.”
Latest figures from an industry survey by the ESO suggest the introduction of proposed reforms could see the queue reduce to somewhere between 240 to 460GW, but Ofgem said the current proposals may not sufficiently reduce the queue size and “may not enable material improvements to the connection dates of viable, Net-Zero-aligned projects”.
Read more